8
April : Notice of Intent to prepare a Draft Programmatic
Environmental Impact Statement (DPEIS) published in Federal
Register (Vol. 69, No. 68 - pgs 18552 – 18554) |
 |
19-23
April: Scoping Meetings for DPEIS |
 |
26
April – 4 June: Prepare Preliminary Draft LCA
Study Report and DPEIS |
 |
4-25
June: Internal review of Report and DPEIS |
 |
2
July: Submit draft report / DPEIS to EPA |
 |
9
July to 23 August: 45-day Study Report and DPEIS Public
Review and Comment period |
 |
24
August to 17 October: Respond to comments on draft
report; prepare final report / Final PEIS |
 |
22
Oct – 22 Nov: Corps’ Internal Review of
Main Report and FPEIS |
 |
5
Nov: Notice of Availability of LCA Main Report and
FPEIS in Federal Register |
 |
5
Nov – 6 Dec: 30-day state, agency and public
review and comment period |
 |
7
Dec – 14 Dec: Respond to state, agency and public
comments |
 |
15
Dec: Final MRC Report Signed |
 |
31
Jan 05: Signed Chief of Engineers Report transmitted
to Assistant Secretary of the Army (Civil Works) |
| |
|
| |
|